Rockwell Implements Strategic Equipment at Saxendrift

May 22, 2012 5:00 AM   By Deena Taylor
Comment Comment Email Email Print Print Facebook Facebook Twitter Twitter Share Share
RAPAPORT... Rockwell Diamonds implemented a new in-field screen and a bulk x-ray and single particle sorter plant at its Saxendrift diamond mine.  These two strategic projects were the first capital expenses approved by the company's board for implementation by the new management team.

The in-field screen, which was commissioned to address the high-sand content in the gravel that was impacting the mine's ability to achieve its productions targets, is designed to treat higher instances of sand and moisture while maintaining the required processing rates. Another positive impact of the new in-field screen comes from the enhanced pan-plant efficiency due to the higher-quality gravels, cleared of excess sand and small particles being fed into the plant, explained Rockwell's chief executive, James Campbell. He noted that the company is now in a position to consider mining certain blocks that would have been prohibitive earlier.

The in-field screen has enabled the company to increase its monthly volume throughput by over 30 percent while maintaining operating costs at the same level despite rising fuel prices, wage increases and an aging mining fleet in need of more maintenance.

Rockwell also implemented bulk x-ray technology aimed at improving concentrate efficiency and final sorting of diamond bearing ore in mid-April, with encouraging results so far. This strategic initiative is based on a high throughput Bourevestnik (BV) sorter and one BV single particle sorter. The project, which cost Rockwell $1.5 million, began processing old recovery tailings at Saxendrift on April 16, and has recovered a total of 316 stones totaling 1,109 carats in the first month of production. This includes 14 stones in excess of 10 carats with the largest stone weighing 52.67 carats, Rockwell said.

These projects, if successful will be applied to Rockwell's undeveloped, Middle Orange properties next.
Tags: Deena Taylor, Rockwell, Saxendrift
Similar Articles
Jwaneng Mine, BotswanaDe Beers 1Q Production +18%
Apr 24, 2014
De Beers production rose 18 percent year on year to 7.532 million carats...
Similar Videos
Explorers Jump Start Projects, Damas Designs for Spring
Jan 30, 2013
Gemfields completed its acquisition of Faberge this week. Emerald production...
fluor Fluor Completes Jwaneng... diamonds Diamond Explorers Update... IDCMR Martin Rapaport Presentation...
Comments: (0)  Add comment Add Comment
Arrange Comments Last to First
© Copyright 1978-2014 by Martin Rapaport. All rights reserved. Index®, RapNet®, Rapaport®, PriceGrid™, Diamonds.Net™, and JNS®; are TradeMarks of Martin Rapaport.
While the information presented is from sources we believe reliable, we do not guarantee the accuracy or validity of any information presented by Rapaport or the views expressed by users of our internet service.