Firestone’s Liqhobong Mine Set for 4Q Production Start
Mar 21, 2016 9:24 AM
By Rapaport News
|
|
RAPAPORT... Firestone Diamonds said the Liqhobong Diamond Mine in
Lesotho is on track for production to start in the fourth quarter, with plans
in place to recover 1 million carats per year.
The project
was 68-percent complete as of the end of February and remains on budget, the
diamond development company said in a statement March 16. Firestone also
reported its loss grew 2.5 percent year on year to $4.6 million in the six
months to December 31.
“The six
months to 31 December saw substantial development at Liqhobong and importantly,
we have continued this into 2016,” said Stuart Brown, Firestone’s chief
executive officer.
“2016 will be
an exciting year for the company as we make our way to our goal of initial
production in the fourth quarter and to becoming a leading mid-tier diamond
miner, recovering one million carats per annum."
|
|
|
|
|
|